Approval Procedure for Steam Pipeline drawing and Erection Permission, Manufacturing Drawing, Certification of Manufacturing and Tests under the Boiler Act,1923

Approval Procedure for Steam Pipeline drawing and Erection Permission, Manufacturing Drawing Under the Boiler Act 1923.


Step 1. Visit RajFAB web application at www.rajfab.rajasthan.gov.in and select Citizen in login window. OR
Step 2. Register and make user ID & password on Single Sign On to use the RajFAB application.
Step 3. You have to login first on Rajasthan Single Sign On and then select RajFAB icon in Single Sign On Dashboard to use RajFAB application.
Please note that Business Registration Number (BRN) from http://br.raj.nic.in and Labour Identification Number (LIN) from https://shramsuvidha.gov.in/home are needed to use RajFAB web application.
Step 4. For Steam pipeline approval click on Steam Pipeline in left menu or Click Paperless services shown at top navigation bar for erection permission or Manufacturing Drawing approval and then select desired service.
Step 5. Fill in all mandatory fields marked as *
Step 6. Attach required documents. (shown in list below ⇓)
Step 7. Now click Submit button.
Step 8. You will see an acknowledgement with your application ID. You will also see the same application ID as a link at your dashboard. You can also check the status of your application in the same row.
Step 9. Click the above link to see your application and an audit trail at the bottom of the application to check the actions taken on the application
Step 10. In case any clarification asked then you can see details in audit trail and can submit online compliance
Step 11. After approval of your application you can download approval letter online
Step 12. Any third party can verify this approval online in public domain at www.rajfab.rajasthan.gov.in by using application ID
Step 13. To know about time limit Click Here

Departmental procedure for application Steam Pipeline and Erection Permission, Manufacturing Drawing Under the Boiler Act 1923.


1 Application is received by the designated clerk who checks the attached documents and forwards the application to the examining officer
2. After examination, the examining officer sends application to Chief Inspector If any observation is made by the inspecting officer then the clarification is sent online to comply with
3. Approval is issued online.

Procedure for Issuing of IBR Certificate of Manufacturing and Tests under the Boilers Act 1923


1. Concerned Area officer inspects and take tests at site of manufacturing.
2. The Manufacturer submits the duly signed Certificate along with test certificates of IBR Material online alongwith required fee to Concerned Area officer.
3. Area officer submit duly signed certificate to Chief Inspector for countersignature.
4. Application is received by the designated clerk who check the attached documents and forwards the application to the examining officer
5. After examining the certificate, the examining officer send application to chief Inspector for countersignature.
6. Chief Inspector countersigns the certificates.
7. Citizen can download the certificate.

List of document for Approval of Steam Pipeline.

For the approval of Steam Pipeline / erection permission under Boilers Act, 1923 & Indian Boiler Regulations, 1950, submit scanned copy of the following documents:

  1. Isomatric Drawing(s) with list of material shown on the drawing
  2. Welding Procedures and diagrams with suitable notes
  3. Approval letter of Boiler repairer/ Erector
  4. Consent letter of Boiler repairer/ Erector to carry out the work
  5. Click here to see fees
Click here to see CHECKLIST and inspection procedure

List of document for Manufacturing Drawings under Boilers Act, 1923 & Indian Boiler Regulations, 1950.

For the approval of Manufacturing Drawings under Boilers Act, 1923 & Indian Boiler Regulations, 1950, submit scanned copy of the following documents:

  1. Detailed Engineering Drawing(s) with necessary cross sections with list of material shown on the drawing
  2. Welding Procedures and diagrams with suitable notes
  3. Approval letter of Manufacturing Permission
  4. Click here to see fees
Click here to see CHECKLIST and inspection procedure